A HOPE FOR THE FUTURE

Greenalia Wind Power is a company focused on the promotion and production of electric with Wind farms.

0MW
Under Construction
0MW
Backlog
0MW
Advanced Development
0MW
Total

Phase meaning and scope:

Early Stage: Projects with possibilities to reach agreements on land and grid access.

Advanced Development: Projects with 50% probability to obtain agreements on land and 90% probability to obtain grid connection.

Backlog: Projects with land agreements and grid connection, 90% of possibilities to obtain permits, and a defined price scheme (PPA, auction, …) or lenders term sheet.

Under Construction: Projects with NTP (Notice to Proceed) or LNTP given.

IPP / Operation: Projects in operation / Brownfield.